Solid Waste Management Center, Dental Clinic Replacement, (DG3), Diego Garcia, B.I.O.T.

Project A - Dental Clinic Replacement Project Description
This project included minor selective site demolition, concrete foundation and slabs, reinforced concrete masonry and structural steel frame (4,850 SF), modified bitumen roofing over rigid insulation and metal deck, exterior painting, aluminum windows, aluminum storefront entry, steel doors, wood doors, overhead coiling grille, masonry walls, metal studs and gypsum board walls, interior finishes, electrical power and lighting, HVAC systems, plumbing systems, fire sprinkler and alarm systems, and incidental related work.  Site work included fire water service, potable water service, sanitary sewer service, underground electrical power service, exterior lighting, paving and miscellaneous incidental related work.

Dental Clinic

Project B – Solid Waste Management Center
Project B work included the construction of a sanitary landfill with leachate collection and disposal system, an incinerator facility (13,500 SF), recycling facility (1,700 SF), fencing, access roads, truck scale, control building, electrical power system, communications system, water system, fire protection system, sewage collection system, closure on existing landfill, and incidental related work.

Solid Waste Management, In Progress

Contract Number:
N62742-05-C-1303

Issued By:
U.S. Navy

Contract Amount:
$14,983,446

Contract Award Date:
May 13, 2005

Contract Start Date:
May 13, 2005

Contract Completion Date:
May 13, 2007