IDIQ Contract for Construction & Services at U.S.  Army Kwajalein Atoll / Reagan Test Site

Task Order #1, Emergency Services Facility, Meck Island
Provide rapid response capability for design/build of the Emergency Services Facility to house a single company fire department and the medical services operation on Meck Island. This facility includes latrines, day functions and a medical treatment area, a training area, sleeping rooms for sixty (personnel maximum), a cooking/dining room, an administration area, working and storage areas, and separately contained mechanical, electrical, and communications rooms. The facility was constructed using a reinforced concrete foundation and industrial floor slab.  It has precast concrete walls, a precast concrete roof with rigid insulation and air conditioning.  Supporting facilities include utilities (electricity, water, sewer, and communications), roads, sidewalks, and site improvements.
In Progress
Complete
Task Order #2, Relocation of the Saltwater Intake Line, Roi-Namur Island.
Perform all work necessary to cut and cap two existing 30 diameter saltwater intake pipes from Roi-Namur Island fuel pier and install approximately 400 LF of new 28 saltwater intake lines.  Restore damaged pavement and shoreline rubble armoring.  Work included demolition, excavation, trenching, dredging, shoreline and coastal protection waste management, concrete, structural steel and saltwater intake pipe and fittings.
Saltwater Intake Pipeline

Contract Number:
W9128A-06-D-0002

Issued By:
U.S. Army Corp of Engineers

Contract Amount:
$4,380,000

Contract Award Date:
Apr 20, 2006

Contract Start Date:
Jun 05, 2006

Contract Completion Date:
Apr 19, 2008